±3 sigma precision Question - Need help

A project manager made 3-point estimates on a critical path and found the following results:

Assuming ±3 sigma precision level for each estimate, what is the standard deviation of the allover path?

 
  App. 4.2 days
  App. 5.2 days
  App. 6.2 days
  You can not derive the path standard deviation from the information given.

 

admin's picture

This is an FAQ , check this http://pmzilla.com/3-point-estimates