Answer require for the question

Hi,

Can anybody help me please to solve this question with detail.

You are estimating the cost for the website development work package. Most likely the cost will be $1,000. However, there is a chance it can cost as much as $ 1,800 or as little as $500. What is the best estimate for work package ?

A. $1,050

B $1,100

C $1,000

D $3,300

Answer is "A", but i don’t understand how its come.

0
Your rating: None

Ans should be A. Using the

Ans should be A.

Using the formula for PERT = P+4M+O/6 = (500 + 4* 1000+ 1800)/6=1050

Little further assistance require

Thanks for update. but i am still in little bit confusion how you determine from the question that P = 500 and O = 1800.

M = 1000 its understood.

Low end of the range is

Low end of the range is pessimitic = 500, high end is optimistic 1800.

It says Cost, therefore low end is Optimistic !

 It says Cost, therefore,

low end is Optimistic = 500  &

High end is pessimistic = 1800

 

Thanks for support

Thanks for assistance, now its clear and understandable.