You are estimating the cost for the website development work package. Most likely the cost will be $1,000. However, there is a chance it can cost as much as $ 1,800 or as little as $500. What is the best estimate for work package ?
A. $1,050
B $1,100
C $1,000
D $3,300
Answer is "A", but i don’t understand how its come.


Ans should be A. Using the
Ans should be A.
Using the formula for PERT = P+4M+O/6 = (500 + 4* 1000+ 1800)/6=1050
Little further assistance require
Thanks for update. but i am still in little bit confusion how you determine from the question that P = 500 and O = 1800.
M = 1000 its understood.
Low end of the range is
Low end of the range is pessimitic = 500, high end is optimistic 1800.
It says Cost, therefore low end is Optimistic !
It says Cost, therefore,
low end is Optimistic = 500 &
High end is pessimistic = 1800
Thanks for support