CertChamp - Closure question

you are in charge of a project to build a bridge across a river. You are midway through the project. However due to changes in environmental laws the project can no longer proceed and would need to terminated. Executive management has asked you to document the level of work completed for the project. This would be done in which of the processes ?

A. Project closure
B. Contract Closure
C. Project charter
D. Scope Verification

what do you think here ?

Correct answer : A. Project closure

When any project gets terminated, PM starts the project closure process is done and the following tasks are completed as a part of this process
1. close procurement and make payments to your vendors/contractors
2. document the status of work completed and accepted
3. document the reason for project termination
4. gather lesson learnt
5. update the project records
6. report final performance if any
7. release resources
8. update the organizational process assets
9. solicit feedback from customer

Hope this helps!

Yes lessons learned, Index and archive records - are all done in Project closure / close phase

 

I really agree with you guys, i think also it's part of closure

 

BUT

 

Cert Champ says it is Scope Verificaiton

 

this is wrong... I dont recommend CertChamp !