Charter
Submitted by Jp2786 on Mon, 05/26/2014 - 21:11
1. All of the following are purposes of project charter except?
a) It establishes the project
b) It identifies the product acceptance criteria
c) It gives the project manager authority
d) It includes stakeholder’s requirements
View pls
Forums:


Sundara.damaraj...
Tue, 05/27/2014 - 00:37
Permalink
Charter
B
Please tell me the source of this question.
Jp2786
Tue, 05/27/2014 - 02:23
Permalink
Rational?
From Rita exam
Could you please let me know how u arrived at B.
If you see PMBOk page 72 it says success criteria as one of the contents in a project charter.
That's why Im confused!
Thanks for your response.
admin
Tue, 05/27/2014 - 03:42
Permalink
Success criteria is different
Success criteria is different from Acceptance criteria. Acceptance criteria will be worked out later when scope is finalized and you know what to check for before accepting the project /product.
Success criteria is high level, in the sense, it only says that cost reduction of 20% to be achieved or Customer responsiveness to increase by 5% etc.
Jp2786
Tue, 05/27/2014 - 03:43
Permalink
Perfect!
Yes, I get it now. Thanks a lot admin.