Charter

1.       All of the following are purposes of project charter except?

a) It establishes the project

b) It identifies the product acceptance criteria

c) It gives the project manager authority

d) It includes stakeholder’s requirements

View pls

B

Please tell me the source of this question.

From Rita exam

Could you please let me know how u arrived at B.

If you see PMBOk page 72 it says success criteria as one of the contents in a project charter.

That's why Im confused!

 

Thanks for your response.

admin's picture

Success criteria is different from Acceptance criteria. Acceptance criteria will be worked out later when scope is finalized and you know what to check for before accepting the project /product.

Success criteria is high level, in the sense, it only says that cost reduction of 20% to be achieved or Customer responsiveness to increase by 5% etc.

Yes, I get it now. Thanks a lot admin.