Check options , no one is right answer

Hi


This is q no 125 of Head First.PDF-- it is simply direct ITTO based question.


Please Check options , no one is right answer.


125. Which of the following is NOT an input of the Administer Procurements process?
A. Work Performance Information
B. Procurement Management Plan
C. Contract
D. Procurement Documents

Mr.Pawar,

I would choose B as the best option. Because Project Management Plan is a Direct Input to Administer procurements.Having said that, Procurement management Plan is part of Project Management Plan but not the other way around.
If the options had Project management plan , then you are right no one is the right answer. In real exam we may get one or two like this all we need to remember is that Project management plan has all subsidiary plans, not the other way around.

Dear Respected Pawarji Sir, et al:-


 


This Question is wrong. Ideally it should be, "What is the input to Administer Procurements"?


 


And the answer is Proc Documents or D. The other three, A< B< C are NOT used as an input to Administer  Procurements.


 


No wonder that the soothsayers of the likes of  Admin, SS, RD, Karthik, et al have always advocated the cause of quality questions from quality providers :)


 


Best, KK...