Sample question of PMPQ
Submitted by pmtraining2012 on Thu, 10/18/2012 - 21:31
This is a question included in PMPQ Lite version:
You are assigned as the project manager for a new and highly visible project. You do not have any experience with the type of project assigned. In this situation, the best first step would be to:
A) Use your personal intuition
B) Develop a WBS
C) Obtain and review historical project records
D) Rely on the sponsor for all project planning
To see the answer go to www.pmtraining.es/PMPQeng.htm, try PMPQ Lite, and go to question number 9 of Integration (Knowledge Areas section).
Regards
Forums:


prashant.spce
Fri, 10/19/2012 - 05:25
Permalink
Re:Sample question of PMPQ
Hi,
My answer is C.
Thanks and Regards
Prashant
ssundar
Fri, 10/19/2012 - 16:09
Permalink
I too believe, answer is C.
I too believe, answer is C.
admin
Fri, 10/19/2012 - 17:50
Permalink
C should be the correct
C should be the correct answer.
pmtraining2012
Fri, 10/19/2012 - 20:33
Permalink
You are correct
The correct answer is C.
Exposition: Project files, databases and lessons learned data may assist in the initial planning process.