Developing alternative activity sequence exemplifies
A)Risk aversion
B)Workaround
C)Rolling wave
D)Contingency planning
cnppmp
Mon, 05/20/2013 - 12:14
Permalink
D? for soemthing fails after risk response planning you have contingency plan to look at>
Regards
CN Patil
vijayavadrevu
Mon, 05/20/2013 - 12:18
You are right. I have chosen the option, Workaround. Can you please elaborate as to why work around is not correct and contingency plan is right?
sanskrit
Mon, 05/20/2013 - 12:58
D i.e. Contingency planning
Work around is what you do when a unidentified / unknown risk occures, It's not PLANNED risk response
Mon, 05/20/2013 - 14:15
Yes I understand. Thank You
cnppmp
Mon, 05/20/2013 - 12:14
Permalink
D
D? for soemthing fails after risk response planning you have contingency plan to look at>
Regards
CN Patil
vijayavadrevu
Mon, 05/20/2013 - 12:18
Permalink
You are right. I have chosen
You are right. I have chosen the option, Workaround. Can you please elaborate as to why work around is not correct and contingency plan is right?
sanskrit
Mon, 05/20/2013 - 12:58
Permalink
D ?
D i.e. Contingency planning
Work around is what you do when a unidentified / unknown risk occures, It's not PLANNED risk response
vijayavadrevu
Mon, 05/20/2013 - 14:15
Permalink
Yes I understand. Thank You
Yes I understand. Thank You