Confusing - pls clarify
James has been managing a hotel construction project in a busy street. He is in the process of estimating activity durations for building walls and calculates the most likely estimate as 15 days. If pre-fabricated material is used, it would take no more than 12 days to finish the work. However, the work may be delayed and could take up to 18 days if less experienced construction workers are used to build the walls. But, the engineer in-charge of the work estimates the duration as 8 days when pre-fabricated material is used. What is the expected duration of building walls using the three-point (PERT) estimate, if the engineer's estimation is assumed correct?
A. 12 days
B. 11 days
C. 16 days
D. 14 days
i got ans 12 days but it is not rather 14


hkakumanu@gmail.com
Tue, 11/25/2014 - 16:22
Permalink
(P+4M+O)/6 = (8+4*15+18)/6 =
(P+4M+O)/6 = (8+4*15+18)/6 = 14.33 i.e., 14 days.
dipti1pmp
Wed, 11/26/2014 - 05:39
Permalink
will not m=12?
from sentence:
If pre-fabricated material is used, it would take no more than 12 days to finish the work.
m=12?
jwhelan
Tue, 11/25/2014 - 17:08
Permalink
PERT
PERT uses weighed average three point estimated. thats the beta calculation not the triagular. so we take the new 8 optimistic, 4 times the most likely 15 plus the pessimistic 18 and divide by 6.
thats O+4M+P / 6 = PERT
8 + 4(15)+18 / 6 = PERT
8 + 60 + 18 / 6 = PERT
14 = PERT
dipti1pmp
Wed, 11/26/2014 - 05:38
Permalink
will not m be 12
reading sentence: If pre-fabricated material is used, it would take no more than 12 days to finish the work.
will not m=12?
ovhirup
Wed, 11/26/2014 - 07:43
Permalink
Answer
Answer
You need to chosse the best answer.
Now assumption is "if the engineer's estimation is assumed correct"
that is 8 NOT 12.
so Three point estimation goes = (8+15+18)/3=41/3=13.6667
We choose the best answer , that is 14 , D
dipti1pmp
Wed, 11/26/2014 - 08:28
Permalink
above formula is wrong
we must be using the =p+4m+6o /6 right?
dipti1pmp
Wed, 11/26/2014 - 08:29
Permalink
sorry that was
sorry that was p+4m+o / 6
ovhirup
Wed, 11/26/2014 - 11:46
Permalink
PERT Beta 3-point = (Pessimistic + (4 * Most Likely) + Optimistic) / 6
PERT Triangular 3-point = (Pessimistic + Most Likely + Optimistic) / 3
The question should mention what type of estimation is being asked.
I assumed PERT Triangular 3-point , The question is not complete, it should mention the estimation technique.
dipti1pmp
Wed, 11/26/2014 - 12:46
Permalink
thumb rule
when the question does not mention we must be using the weightd beta
ovhirup
Wed, 11/26/2014 - 13:39
Permalink
Optimistic is 8 not 12
So using Beta estimate
PERT=(8+4*15+18)/6= 86/6= 14