None of them pose any risk to the seller as he is guaranteed to get reimbursed for the costs incurred. The only questions is: Which one offers lowest profit margin for the seller? It is CPFF.
Submitted by chowdary2104 on Thu, 03/18/2010 - 14:06.
CPAF is the riskiest for the seller among other options. Here there is no guarantee for Award Fees. It depends on the Buyer. The seller always should be vigilant and satisfy the buyer in order to get his fee.Regards,CHOWDARY
Submitted by yassersaleh on Thu, 03/18/2010 - 23:59.
_____________ is the riskiest of the cost plus contracts for the seller.
(A) CPPC
(B) CPFF
(C) CPAF
(D) CPIF
Answer
(D) CPIF (In CPIF contracts, if the final costs are less or greater than original estimated costs, then both buyer and seller share costs from the departures based upon a prenegotiated cost sharing formula) .
None of them pose any risk
None of them pose any risk to the seller as he is guaranteed to get reimbursed for the costs incurred. The only questions is: Which one offers lowest profit margin for the seller? It is CPFF.
Chandra
CPAF is the riskiest for seller among those
Yasser, What is the
Yasser,
What is the correct answer and explanation?
Chandra
II guess it should be b
cost plus contracts Question
_____________ is the riskiest of the cost plus contracts for the seller.
(A) CPPC
(B) CPFF
(C) CPAF
(D) CPIF
Answer
(D) CPIF (In CPIF contracts, if the final costs are less or greater than original estimated costs, then both buyer and seller share costs from the departures based upon a prenegotiated cost sharing formula) .