1) A project has a critical path of twenty-three weeks. What is the impact on the duration of the critical path if the management wants you to complete the project in twenty weeks?
- Increases by three weeks.
- Decreases by three weeks.
- Remains the same.
- Cannot be determined
Forums:


san
Fri, 05/24/2013 - 12:26
Permalink
There will not be any chane
There will not be any chane in the critical path.This could be remains same
sanskrit
Sat, 05/25/2013 - 05:01
Permalink
3. Remains the same.
You can reduce the duration by 3 weeks by crashing or fast tracking
cnppmp
Sat, 05/25/2013 - 11:25
Permalink
it says impact on the duration
I would like to know the answer mentioned ...
If the question was what is the impact on the critical path, then it would have been 'no change'.
Regards
CN Patil