critical path

1)      A project has a critical path of twenty-three weeks. What is the impact on the duration of the critical path if the management wants you to complete the project in twenty weeks?

  1. Increases by three weeks.
  2. Decreases by three weeks.
  3. Remains the same.
  4. Cannot be determined

There will not be any chane in the critical path.This could be remains same

 You can reduce the duration by 3 weeks by crashing or fast tracking

cnppmp's picture

I would like to know the answer mentioned ...


If the question was what  is the impact on the critical path, then it would have been 'no change'.


Regards


CN Patil