You are in the test phase of your software project, and the project sponsor has requested a definitive estimate of when your project will be completed. The most likely estimated duration is 30 days. Which of the following duration estimations will you give to your sponsor?
- 29 - 31 days
- 24 - 36 days
- 20 - 40 days
- 15 - 45 days
Forums:


san
Fri, 05/24/2013 - 11:53
Permalink
This could be 29 to 31 days
This could be 29 to 31 days
vijayavadrevu
Fri, 05/24/2013 - 18:14
Permalink
It looks like you have
It looks like you have considered -5 to +10 percent. The reason I have posted this question is , in PMBOK, though not mentioned as Definitive estimate explicitly, the range is given as -10 to +10 %. The same is case in RITA's book too
Hence need clarification whether to take -5 to +10 % or -10 to + 10 %?