difference between BAC and PMB
Dear all ,
Kindly clear my doubt.
I had a mock exam question.
A railroad construction project is under execution. The project manager is using Earned value Technique to measure the project performance. The total planned value of the project is known as:
A. Performance measurement baseline
B.Earned Value
C. Budget at completion
D. Estimate at Completion.
my answer was A but the key gave choice C Budget at completion.
also gave the reference PMBOK page no : 182. first para last sentence
"Planned value. Planned value (PV) is the authorized budget assigned to the work to be accomplished


crushPMP
Sat, 05/04/2013 - 01:19
Permalink
Answer is definitely C.
Answer is definitely C. BAC
PMB is a combination of scope baseline + schedule baseline + cost baseline