EAC Question
Submitted by stanleyhk on Sun, 09/09/2012 - 14:10
A project was budgeted at $1,000,000. Meanwhile, the project is executed, and
the following current figures have been assessed:
PV: $500,000
EV: $450,000
AC: $550,000
Assuming that the cost variance was caused by one-time cost drivers, which are
no more effective, what estimate at completion (EaC) can you derive from these
figures?
82
a. $900,000
b. $1,000,000
c. $1,100,000
d. $1,222,222
Answer is c but why?
Forums:


aliweb
Sun, 09/09/2012 - 16:31
Permalink
Answer is C because variance
Answer is C because variance was one-time thing and will not continue. Which means the variance is atypical and when variance is one-time/atypical then you use the following formula to calculate EAC.
EAC = AC + (BAC-EV)