ETC
Submitted by pciarro on Mon, 01/20/2014 - 09:19
Hi all,
I've stumbled upon this question:
---
You know that BAC = 375, PV = 300, AC = 200, and EV = 250. Variances that have occurred on the project to date are not expected to continue. What is the ETC?
---
I think there are two answers:
ETC = BAT - EV
ETC = 375 - 250 = 125
or...
CPI = EV/AC
CPI= 250/200 = 1.25
EAC = BAC/CPI
EAC = 375/1.25 = 300
ETC = EAC - AC
ETC = 300 - 200 = 100
What am I missing?
Forums:


signor_rk
Mon, 08/11/2014 - 14:47
Permalink
ETC Calculation
Since the same variance is not going to continue , I would rather choose the formula :
ETC = EAC - AC
= (AC + BAC - EV) - AC
= BAC - EV
= 375 - 250
= 125
Regards,
Ranjit
Frances Tessler
Thu, 08/14/2014 - 17:06
Permalink
ETC
You need EAC first> EAC= BAC/CPI then ETC=ETC-AC. You would have to calculate out CPI first. which is EV/AC. Then EAC then ETC