ETC how would you calculate this question

Budget at completion=$1000
Earned value=500
Cost performance index=0.5
Estimate to Completion is ???

Thanks for the help.

EV=500
CPI=.5
BAC=1000

EAC=BAC/CPI
= 1000/.5

= 2000$

saketbansal's picture