EV Calculation

For a project, the following earned value data have been assessed:
AC: $ 4,000,000
CV: $ -500,000
SPI: 1.12
BaC: $ 9,650,000

What is the earned value of the project?

o $3,000,000
o $3,500,000
o $4,480,000
o $5,650,000

Any help please?

 

CV = EV-AC

-500000 = X-4 000,000

X = $-3,500,000

 $3,500,000 is the answer.