EVM
Submitted by sspawar on Tue, 07/24/2012 - 12:20
One of your project has BAC= 270000.. In a point of time AC measured 100000. while CPI was 0.90. What will be the EAC of your project if later part CPI is measured 1.06.
- 260000
- 270000
- 300000
- None of above
Forums:


RaviDatt
Tue, 07/24/2012 - 12:28
Permalink
I would go with B.
I would go with B.
Ramana_99
Tue, 07/24/2012 - 12:59
Permalink
My Answer is...
EAC = BAC / Cumulative CPI
= 270000 / 1.06
= 254716.98
Answer is 4. (none of the above)
Regards,
Ramana
krantikumar50
Tue, 07/24/2012 - 13:27
Permalink
Maths...
Respected Pawarji Sir,
Maths is totally an unknown territory till now. Let me get little comfortable on this first and then will answer you.
Warmly, KK...
sspawar
Tue, 07/24/2012 - 14:31
Permalink
Ravi is right
Ravi is next to Dibankar
He has already solved here I saw later
RaviDatt
Tue, 07/24/2012 - 13:48
Permalink
BAC = 270000AC = 100000CPI
BAC = 270000
AC = 100000
CPI = 0.9
EV=CPI * AC = 90000
NEW CPI = 1.06
EAC=AC+((BAC-EV)/CPI)
100000+(270000-90000)/1.06= 269811
270000 APPROX
B?
tmanivannan
Tue, 10/16/2012 - 20:59
Permalink
EVM Question
First time, I am seeing this formula. So we need to understand the scenario and have to apply respective ETC.
EAC=AC + ( (BAC-EV) / CPI)
Is the anser 'B' correct one ?
sspawar
Wed, 10/17/2012 - 01:26
Permalink
Its derivation of your known
Its derivation of
your known formula
TCPI = (BAC-EV)/(EAC-AC)
In question TCPI is written as new CPI
EAC-AC = (BAC-EV)/CPInew
EAC = ((BAC-EV)/CPI) +AC
CPI1st =EV/AC
EV = 100000X0.90(1ST CPI) = 90000
={(270000-90000)/1.06} +100000
= (180000/1.06) +100000
= 169811 +100000
= 269811 ~27000
tmanivannan
Wed, 10/17/2012 - 02:39
Permalink
Awesome..
Thank you, Pawar. From this, I clearly understood the formula and idenfied some gaps on my EVM.
Your reply really helps me and Thanks to this forum also.