EVM metric

A)SPI

B)CPI

C)CV

D)SV

 

Iam confused between CPI and SPI. Can someone help with reasoning?

 CPI.

Page: 183 PMbok.

May I know the source of this qn pls?

Thank You. It is from one of the sources given in pmzilla free exam links tab

 Thanks.

 CPI-- tells you whether you are over budget or under budget

SPI-tells you whether the project is on schedule or behind schedule

 

and CPI is the most important one