Please refer to the diagram given below (all units are in days):
1)
What is the project float if management wants to complete this project within 13 days?
- 0 days
- - 3 days
- 2 days
- Cannot be determined, because information given in the question is incomplete
Forums:


san
Fri, 05/24/2013 - 11:36
Permalink
Ans: -3 days
Ans: -3 days
san
Fri, 05/24/2013 - 11:54
Permalink
13-16
13-16