You are managing a software development project. You want to create the basis that will be used later on for estimating, scheduling, executing, monitoring, and controlling the project work. Which process performs this activity?

a) Create WBS
b) Define Scope
c) Define Activities
d) Create Project Management Plan

------------------------------
Hint: Estimating is performed when the activities are defined and the schedule is prepared.
------------------------------

All our questions are updated to the latest PMBOK® Guide standard. Stop by at http://free.pm-exam-simulator.com and try the PMP Exam Simulator free for 3 days. We also offer 110 free questions at http://www.free-pm-exam-questions.com. We are a PMI Registered Education Provider.

Please click here for the correct answer and explanation.

Until next time,
Cornelius Fichtner, PMP
President, OSP International LLC - http://www.project-management-prepcast.com

Tried with 1 Simulator Exam they are good.

cnppmp's picture

This is pertaining to Integration management and Create project management planning is part of this KA. Also, project management plan has all subsidiary plans and beocmes input for all the processes of process groups and get updates to it.

so it should be D