help with this question pls

 In shortening the project duration,the first action to take is to

A) Change the project scope

B) Crash as many activities as possible

c) Fast-track activities on critical path

D) cuonsume the float on critical path

 I know its seems simple but there is a confusion please what is the corect answer and please with a little explanation.

The answer is C.

A) Change the project scope - you want to explore all possible solutions before changing project scope.

B) Crash as many activities as possible - you would want to only crash those on the critical path, and also you would always fast-track activities first, as it consumes less resources (albeit higher risk)

D) consume the float on critical path - the critical path has no float.

 

Hope this helps.

 Fast Tracking is the Best option in the given List of options so the answer is C.

fast track the item on Critical parth I think you only  Crash critical parth item I think B

I think if chose fast-track you enhance risk of project implementation, that’s why you have to use Crash

the answer - B

i think the correct answer is C and i second what the previous members with C option has to say. Please can you advise what was the correct answer