In shortening the project duration,the first action to take is to
A) Change the project scope
B) Crash as many activities as possible
c) Fast-track activities on critical path
D) cuonsume the float on critical path
I know its seems simple but there is a confusion please what is the corect answer and please with a little explanation.


lemailme
Fri, 07/12/2013 - 20:59
Permalink
The answer is C.A) Change the
The answer is C.
A) Change the project scope - you want to explore all possible solutions before changing project scope.
B) Crash as many activities as possible - you would want to only crash those on the critical path, and also you would always fast-track activities first, as it consumes less resources (albeit higher risk)
D) consume the float on critical path - the critical path has no float.
Hope this helps.
surendeep_PMP
Sat, 07/13/2013 - 04:08
Permalink
The Answer is C
Fast Tracking is the Best option in the given List of options so the answer is C.
abiodun.lm@gmail.com
Sat, 07/13/2013 - 10:33
Permalink
fast track the item on
fast track the item on Critical parth I think you only Crash critical parth item I think B
Ruslan Kaydashov
Sat, 07/13/2013 - 10:48
Permalink
I think if chose fast-track
I think if chose fast-track you enhance risk of project implementation, that’s why you have to use Crash
the answer - B
nevish
Sun, 07/14/2013 - 09:24
Permalink
fast track
i think the correct answer is C and i second what the previous members with C option has to say. Please can you advise what was the correct answer