Hi, please help me to solve EV question below
Activity A is worth $300, is100% complete and cost $350. Activity B is $100 worth, is 95% complete andactually cost $85 so far. Activity C is worth $ 200, is 75% complete and hascost $ 175 so far. Total Budget is $1500. What is EAC for the activities listed?
Options are
A. $1706
B. $0.88
C. $1685
D. $185


re How to solve listed EV Question
EV=300+95+150(200*.75)=545
AC=350+85+175=610
BAC=1500
CPI= EV/AC=.893
EAC=BAC/CPI =1500/.893 =1685
Thank you for detailed
How to solve listed EV Question
Hi,
Can you please explain, How to calculate this. The Question was no doubt ambigious but the answer is also not clear.
Please explaing the steps you have performed while calculating this EV.
Re how to solve listed ev question
In a large project a single cost baseline can be broken in to mulitple cost baselines say A may be used for tracking production cost, B for purchase cost etc
So in this question Earned Value for the entire project ( measure of work completed) = EV of A+EV of B+EV of C
EV of A = 300 *100/100 = 300 (Activity A is worth $300, is100% complete)
EV of B = 100*95/100 = 95 (Activity B is $100 worth, is 95% complete)
EV of C = 200*75/100 =150 (Activity C is worth $ 200, is 75% complete)
Total EV =300+95+150=545
Total AC=350+85+175=610 (cost of Activity A=350, Activity B=85, Activity C=175)BAC=1500 (Total Budget is $1500 )
CPI= EV/AC=.893
EAC=BAC/CPI =1500/.893 =1685
Please let me know if its still not clear
how to solve listed ev question
Thanks for the explanation.... Actually I was abit confused on ur first explanation.
Thanks alot again..
I saw PMBOK4 mention Four Formula's for EAC and ETC.
In
that case how w
ould we know which formula of EAC or ETC we need. Any good tip.
Re please help me to solve EV question below
How to calculate EAC is very well explained in one of the blog site