Inspection - Verify Scope or Quality Control ?

In order to meet product acceptance criteria you have to perform several activities such as measuring, examining, and verifying including reviews, audits and walkthroughs. The above scenario best describes which process? 

A. Perform Quality Control

B. Verify Scope

C. Perform Quality Assurance

D. Perform Quality Control

 

PMPForSure Answer : B

But these activities are part of inspection and inspection is a tool for Verify Scope as well as Quality Control.

So why the answer is B and not D ?

admin's picture

Since it says acceptance criteria, you pick verify scope over QC. Verify scope is only to ensure product is accepted.

 the terms used r just same as mentioned in PMBOK forT&T of verify scope.

its correct!!!