Learning Curve Theory Question !!
Submitted by maheshgonuguntla on Thu, 01/02/2014 - 07:31
A project manager is considering applying learning curve theory to his project. The project involves designing a number of software modules that are very similar. According to the cost figures that have been collected the first unit required 100 person-hours to design and test. The second unit required 90 person-hours to design and test. How many person-hours will the eighth module take to design and test?
A.90
B.100
C.73
D.172
Forums:


admin
Fri, 01/03/2014 - 03:35
Permalink
Since its applying learning
Since its applying learning curve theory and modules are similar, 8th module should take less than 90 hours, so I guess 73 would be the right answer.