Lets start with an Example , in a software development project
-> Coding is an Discreat Effort, the effort needed to create the deliverable
- Aportioned effort is and effort needed to verify deliverable , so testing is an apportionate effort, the effort we spend in ensuring that discreat effort is producing the right output
- LOE is not directly contributing to the deliverable but it is necessary so that discreate and apportionate effort can product output, so the project management activities falls under this category
thinkval
Wed, 04/24/2013 - 11:29
Permalink
LOE Example Project Management Activities
Lets start with an Example , in a software development project
-> Coding is an Discreat Effort, the effort needed to create the deliverable
- Aportioned effort is and effort needed to verify deliverable , so testing is an apportionate effort, the effort we spend in ensuring that discreat effort is producing the right output
- LOE is not directly contributing to the deliverable but it is necessary so that discreate and apportionate effort can product output, so the project management activities falls under this category
vijayavadrevu
Wed, 04/24/2013 - 11:39
Permalink
Thank YouRegardsVijaya
Thank You
Regards
Vijaya
crushPMP
Wed, 04/24/2013 - 13:54
Permalink
What's the source of this
What's the source of this question, don't see anything like this in PMBOK
sspawar
Wed, 04/24/2013 - 14:09
Permalink
These all 3 are in pmbok
These all 3 are in pmbok 4.p136
wikipedia , google have better description to understand
also may search old posts.