The 2 years project has 200 work packages and a $20,000 budget. After one year, 100 work packages are completed and $10,000 has been spent. Which of the following is TRUE?
 












1.       The project need 50 work package to be completed in 6 months.
2.   Not enough information available.
3.   The project need 50 work package to be completed in 3 months.
4.   The project is on schedule and on budget.


 


any guess?


Regards


CN Patil

crushPMP's picture

 2?

Let's say the 1st 100 WP's completed were the smaller ones and the real tough ones are yet to come in the later half of the project. So ideally you should have completed the 1st 100 easier EP's in less than an year to compensate for the tougher ones coming in the later half. 

Also there is no cost information given if it took $10K to complete those 100 WP's in 1 year or something else.

Nothing much can be inferred out of the given info

B is the correct answer.

There is Not enough information available about the project. What was planned? Is the work packages are same? Therefore Option B is TRUE.
 

This is a question from TechFAQ360 and I came across this and so rember it,

Thanks

Jai

 I am goin with 4. as project is half done in half time period.

But yes, if every WP is not same size, then I am wrong.

lemme know the ans

cnppmp's picture

no enough information.


Regards


CN Patil