Hello,

I am in process of filling my application for PMP exam. I need an advice.

I have worked on 3 releases of same project. How can I write different description because other than diff changes we were working on, most of project work and my roles didnt change. That means project description will not be very differnt from one anothet.

 

Please suggest.

saketbansal's picture

You can make 3 entries and make each as seperate release / project for same product, in such cases we take each release as a project. since it goes through all phases and also produce deliverables.

You will find our this vidoe useful , it elaborates "How to fill Experience Details in PMP Application ?"

https://www.youtube.com/watch?v=2k7AV9dJunk

Chek it out... 

 

Amalhi,
I agree - consider each a unique release, or if more appropriate, a phase.

You have 3 separate entries as each change was a separate release. Use it as such.