Need Clarification.
Submitted by Sundara.damaraj... on Mon, 05/12/2014 - 03:18
You are managing the implementation of ERP software in a factory. Software support must be provided round the clock. You need to schedule the shifts of the crew in such a way that a crew cannot finish their shift until next shift crew has arrived. What type of dependency exists between the shifts?
I have answered as "Finish to Start".
My justification :- Predecessor is "First Crew" Successor is "Next shift Crew"
But the correct answer is "Start to Finish"
Can someone explain this ?
Forums:


anmol2701
Mon, 05/12/2014 - 07:39
Permalink
Start to Finish.
Kindly refer PMBOK 5.
Page no. 156...
"Successor activity cannot finish until a predecessor activity has started" ...
sunku65
Mon, 05/12/2014 - 08:43
Permalink
Hi Anmol,Can you tell me here
sunku65
Mon, 05/12/2014 - 10:46
Permalink
PMzilla server timedout.
PMzilla server timedout.
sunku65
Mon, 05/12/2014 - 10:57
Permalink
PMBOK doest mention anything