Hi Everyone, I'm having trouble trying to figure out the solution to the following questions. Can someone please be kind enough to post the solutions to solving these? I think the main problem I'm having is that the information is given for activities in the project and not as a whole which is throwing me off.
All the questions are based on the below information.
Activity A is worth $300, is 100% complete, and actually cost $350. Activity B is worth $100, 95% complete, and actually cost $85. Activity C is worth $200, is 75% complete, and has cost $175 so far. The total budget is $1500.
First questions asks What is the estimate to complete for the project? Answer is $1075.39
Second question asks What is the cost variance for the project? Answer is -$65
Third question asks What is the schedule variance for the project? Answer is $-55
Fourth question asks What is the total earned value for the project? Answer is $545
Fifth question asks What is the estimate at completion for the project? Answer is $1685.39
Sixth question asks What is the cost performance index for the project? Answer is 0.89
Seventh question asks What is the variance at completion for the project? Answer is $-185.39
Thank you everyone in advance


pkpmp
Tue, 04/15/2014 - 07:09
Permalink
Problem analysis is as follow
Problem analysis is as follow :
1. PV(A)+PV(B)+PV(C) = 300+100+200 = 600
2. EV(A)+EV(B)+EV(C) = 300+95+150 = 545 (Ans of 4th Q)
3. AC(A)+AC(B)+AC(C) = 350+85+175 = 610
4. BAC =1500
Calculations :
EAC = BAC/CPI = BAC*AC/EV = 1500*610/545 = 1685 (Answer of 5th Q)
ETC = EAC - AC = 1685-610 = 1075 (Answer of 1st Q)
CV=EV-AC=545-610 = - 65 (Answer of 2nd Q)
SV = EV-PV = 545-600 = -55 (Ans of 3rd Q)
CPI = EV/AC = 545/610 = 0.89 (Ans of 6th Q)
VAC = BAC - EAC = 1500-1685 = -185 (Ans of 7th Q)
I hope its clear to you....
h.fazel
Tue, 04/15/2014 - 20:48
Permalink
Thank you!
Thank you very much pkpmp! You're solution is very clear and detailed. I fully understand it now. Thank you once again for your help!
mattR
Wed, 04/16/2014 - 03:32
Permalink
Am I crazy or is 1500*610/545
mattR
Wed, 04/16/2014 - 03:43
Permalink
Wrong math?
Am I crazy, or does 1500 * (610/545) = 1678.90?