Negative or Positive Risk Response?

 

Jane is worried about her project because many of her tasks are slowly moving and two critical tasks may have the chance of slippage. She conducts a thorough resource analysis and finds out that there are five resources who will be free next week. She would like to use this as an opportunity to assign those resources to finish her tasks early and prevent the project completion date from slipping. This effort is an instance of which of the following risk response techniques?

  1. Transferring

  2. Sharing

  3. Enhancing

  4. Accepting

Does anybody think that the probablity to slip on critical task is a opportunity and not a threat?

option c

 Prior to evaluate the answer, are we dealing with positive or negative risks?

If the risk of slippage is a negative one could it be responded using positive options?