Which documents located where?

crushPMP's picture

 You are the project manager of a pharmaceutical company responsible for releasing a new drug in the market. While managing the project, you have created several documents (e.g., project management plan, risk registers, cost, schedule, and quality baselines). All these documents should be stored in: 

 
 
  Choice 1 Historical information
 
  Choice 2 Project files
 
  Choice 3 Project or phase closure documents
 
  Choice 4 Configuration management system
 
 
 
You are in the Close Project or Phase of the project. You finalize all activities across all the project management process groups to formally complete the phase. You also update documents, such as project management plan, scope management plan, cost management plan, etc. that are generated from project`s activities. These documents are also referred to as:
 
 
  Choice 1 Project or phase closure documents
 
  Choice 2 Project plan
 
  Choice 3 Historical information
 
  Choice 4        Project records

 For the first question, I would with go with OPTION 2-- Project files

 I would go with  OPTION-1 -PROJECT or Phase closure documents for second question

I would say for

Q1) it is choice 2

Project Files - includes docs like PM Plan, Scope, Schedule..

Q2) it is Choice 3

Historical Info - now the project files become part of the historical info as the project is done.

Choice 4

Choice 4

Choice 4, and

Choice 4

 

I would go with choice 4 for Q1, sicne the configuration management system keeps the track of all the changes to the deliverables. All t mentioned documents are deliverables for the project, which keeps the latest version of the document. He says while managing the project not closure.


The Q2 with choice 4 is because the in peoject closing these are referred as archiving project records.


Regards


CN Patil.

Choice 4 Configuration management system


Choice 4   Project records

 Correct answer??

crushPMP's picture

A1. 2


A2. 1

A1. 2 (yes..a direct question)

A2. I believe choice 3, coz..

Historical information fits the given explanation more..

Also Project/Phase closure documents does not mention those explicitly and it is more about Closure formalities in case of normal  & termination scenario etc.

When you say 'direct question', do you mean to say directly from PMBOK4? I searched a soft copy for 'project files' and could not find an occurrence of it.

 

 pmbok pg 102

Project files, OPA updates

Thanks for the page number reference! Yes, that is a direct question for sure.

Regards.

 

Could you pls tell us the source of this question?

Thanks.

 

crushPMP's picture

 It's from PMStudy Paid exams

Ok, thanks.

 

Regards.