Question on Changes
Submitted by Anonymous (not verified) on Tue, 05/14/2013 - 14:59
The client demands changes to the product specification that will add only two weeks to the critical path. Whcih of the following is the BEST thing for the project maanger to do?
1. Compress the schedule to recover the two weeks
2. Cut the scope to recover two weeks
3. Consult with the sponsor about options
4. Advise the client of the impact of the change
Forums:


crushPMP
Tue, 05/14/2013 - 15:12
Permalink
4
4
sanskrit
Tue, 05/14/2013 - 16:42
Permalink
3
3. Consult with the sponsor about options
As per Ritas book
cnpatilpmp2012 (not verified)
Tue, 05/14/2013 - 17:16
Permalink
Correct is 3,..
It;s from Rita's book. generally we fall for the option 4. But as per Rita's logic, we should have it consulted internally if the question already suggests the 'evaluation' has been done. If option 3 wasn't provided, then the option to go to client to advise on the impact would have neen correct.
I got puzzled thought will ask few people around.
Regards
CN Patil