project close out

In functional organization who among the following is responsible for Project Close-out

A)Project Manager

B)Functional Manager

C)Project Sponsor

D)Project Stakeholder

 

 B. as Functional manager is PM.

cnppmp's picture

Functional organization, the project manager role is limited to project expeditor, so he would be working as assisting to manager responsible for manager, so it should be functional manager. Also, project do not have authority to assign resource, no decision making authority, no authority to sue budget..


 


But little tricky question..


Regards


CN Patil

Yes, Thank You for the explanation. Functional Manager is right. I have answered as Project manager, which is a wrong option