The project work has been completed and the customer has accepted the completed project scope. However, the project status is still incomplete. Which of the following statements could be true?
A)
The project is incomplete because project and product deliverables do not fulfill the requirementsB)
The project must be marked completed as deliverables have already been accepted by the customerC)
The project is marked incomplete till the lessons learned required by the project management office have not been completedD)
The project is incomplete because the project needs to be re-plannedForums:


san
Mon, 05/20/2013 - 13:09
Permalink
This could be C. Lessons
This could be C. Lessons learned document is pending for closure
sanskrit
Mon, 05/20/2013 - 13:12
Permalink
Tricky , C
C should be the Answer Because
In a purely technical sense Lesson Learned is Good Practice, But that it can not be the only reason for the project to be considered as complete.
BUT BUT In this case Option C Says specificallly that " lessons learned required by the project management office "
So that is the reason project can not be marked complete unless it satisfies PMO's requirement