float

Please refer to the diagram given below (all units are in days):

1)      

                     What is the project float if management wants to complete this project within 13 days?

  1. 0 days
  2. - 3 days
  3. 2 days
  4. Cannot be determined, because information given in the question is incomplete

 

 

Ans: -3 days

13-16