Assuming that the critical path of your project has duration of ten days, which of the following cannot affect the project timelines?
- If the project has one critical path, you are able to decrease the duration of the critical path by one day by using a new tool.
- If the project has one critical path, you have to increase the duration of the critical path by one day due to delays.
- If the project has two critical paths, you are able to decrease the duration of one critical path by one day by using a new tool.
- If the project has two critical paths, you have to increase the duration of one critical path by one day due to delays.
Forums:


san
Fri, 05/24/2013 - 14:56
Permalink
Could be 3.Though one of the
Could be 3.
Though one of the critical path decreases(less than 10) and other critical path (=10)remains same.
jvleminc
Mon, 05/27/2013 - 17:33
Permalink
Yep, should be 3:- Only one
Yep, should be 3:
- Only one critical path -> changing it impacts total project timelines -> 1 & 2 false
- Two critical paths -> increasing one makes it the new unique critical path -> impact on total project timeline -> 4 false
- Two critical paths -> decreasing one makes it non-critical and leaves one critical path -> no impact on total project timeline -> 3 true
vijayavadrevu
Mon, 05/27/2013 - 18:17
Permalink
Yes, option 3 is correct
Yes, option 3 is correct