pmstudy question. why critical path is not 15?
Submitted by y0zh on Sat, 05/25/2013 - 13:03
| Question No : 16 |
||
Please refer to the diagram given below (all units are in days):![]() What is the project float if management wants to complete this project within 13 days? |
||
| Choice 1 | 0 days | |
| Choice 2 | - 3 days | |
| Choice 3 | 2 days | |
| Choice 4 | Cannot be determined, because information given in the question is incomplete | |
Forums:



cnppmp
Sat, 05/25/2013 - 13:35
Permalink
-3
-3 since the CP is 16 and if you have to 13 days it would be having negative float of 3.
Draw all possible paths in this network, and you find 1-->2-->3-->5-->7-->E is the CP=16 days
Regards
CN Patil
y0zh
Sat, 05/25/2013 - 14:18
Permalink
was answering quick and
was answering quickly and didn't see Task2-Task3 relationship. thank you for openning eyes
sanskrit
Sat, 05/25/2013 - 14:53
Permalink
Choice 2:
13-16 = - 3days
Choice 2: