formula for free float calculation
Submitted by y0zh on Sat, 05/25/2013 - 18:20
do we use LS - ES of successor? because I found this one formula and got confused:
Free float=ES of the following activity-ES of the present activity-duration of the present activity
http://www.scribd.com/doc/28680971/101-PMP-Sample-Questions-for-the-PMP-Exam
Question 38 and my answer is Task Two free float=7 which is not presented there. Please clarify
Forums:


Fariba
Sat, 05/25/2013 - 21:31
Permalink
confusing formula
I am going through the same questions and it really confused me.
appreciate any help.
Having problem with Question 44 as well. I selected B but the answer is C.
http://www.scribd.com/doc/28680971/101-PMP-Sample-Questions-for-the-PMP-...
vijayavadrevu
Sun, 05/26/2013 - 10:24
Permalink
For question 44,if you
For question 44,
if you observe task 6 is on critical path, float given as 0.
Float = LF-EF or LS-ES
LF and EF are given as 15 & 15.
LS is given as 6.
So ES = LS-Float = 6-0 =6
This is how I have solved the problem.
May be someone can clarify whether this is right approach or not?
vijayavadrevu
Sun, 05/26/2013 - 10:55
Permalink
For question 38, the options
For question 38, the options are referring to free float.
Please refer to the following link where the difference between free float and total float is given. The formula LS-ES , you are referring to, is for the total float
http://pmi.books24x7.com/assetviewer.aspx?bookid=45514&chunkid=397723927
With this, option 2 i.e., task 2 having free float of 6 days is correct.
y0zh
Sun, 05/26/2013 - 13:09
Permalink
Actually, iv mentioned free
Can you provide your variant of formula? EF of predecessor - ES of succesor= free float
vijayavadrevu
Sun, 05/26/2013 - 15:56
Permalink
Have gone through question
Have gone through question 38 referred by you. Could not paste the image
With my little bit of understanding I am providing the 2 solutions. I may be right or wrong in my approach which may have to be confirmed by some experts of this forum. Iam just a learner
Regards
Vijaya
Solution 1:
Please refer to
http://pmi.books24x7.com/assetviewer.aspx?bookid=41937&chunkid=922918066¬eMenuToggle=0&hitSectionMenuToggle=0&leftMenuState=1
For activity 1,
Free Float = Earliest of [ES of successor 2 or ES of successor 3] – EF of activity 1 – 1 day
= 7-6-1=0 option A i.e., 3 days is wrong
For activity 2,
Free Float = ES of activity 4 – EF of activity 2 – 1
= 17-10-1=6 option B i.e., 6 days is correct
For activity 3,
Free Float = ES of activity 4 – EF of activity 3 – 1
=17-16-1 = 0 option C i.e., 9 days is wrong
For activity 4,
Free Float = ES of activity ?? (not given) – EF of activity 4 – 1
Cannot be determined. Option 4 i.e., 5 days is wrong
Solution 2:
Please refer to
http://pmi.books24x7.com/assetviewer.aspx?bookid=45514&chunkid=397723927
Free Float = Earliest ES of Following Activities - ES of Present Activity - Duration of Present Activity
For activity 1,
Free Float = Earliest of [ES of successor 2 or ES of successor 3] - ES of activity 1 - Duration of activity 1
= 7-1-6=0 option A is wrong
For activity 2,
Free Float = ES of activity 4 – ES of activity 2 – Duration of activity 2
= 17-7-4=6 option B is correct
For activity 3,
Free Float = ES of activity 4 – ES of activity 3 – Duration of activity 3
=17- 7-10 = 0 option C is wrong
For activity 4,
Free Float = ES of activity ?? (not given) – EF of activity 4 – 1
Cannot be determined. Option 4 is wrong
Also we have the formula
EF of Activity 1 = ES of Activity 1 + ED of Activity 1 - 1 day
For task 2,
Free Float = ES of activity 4 – EF of activity 2 – 1
= ES of activity 4 – [ES of Activity 2 + ED of Activity 2 - 1 day] -1
=17-[7+4-1]-1
= 17-10-1
= 6
y0zh
Sun, 05/26/2013 - 17:41
Permalink
Question to experts. In the
Question to experts. In the formula above there is -1. Does this mean that we are reffering to the network diagram with 1 day not 0 day start. Sorry, noting from ipad, not able to paste a reference