Hello, I had trouble with question 51 from http://www.pmroadtrip.com/nonsearch/PMRoadTrip_V4Questions.pdf
Is the Risk Register part of the Project Management Plan? Are all project documents considered part of ( or components ) the project management plan?
Forums:


Torontarian
Thu, 07/01/2010 - 17:23
Permalink
Hi There, Please refere to
Hi There,
Please refere to PMBOK 4th adition (page 350), you will find answers to all your questions.
Good luck,
mickcalcara
Thu, 07/01/2010 - 18:01
Permalink
a little more clarification
Hi, Thank you for your reply. I have seen a few sample exam questions with referring to the Risk Register as part ( or component ) of the project plan. Would you agree these questions are not accurate then based on the wording? ( and based on page 350 of the PMBOK) . Such as #51 of http://www.pmroadtrip.com/nonsearch/PMRoadTrip_V4Questions.pdf
Maybe if the question was worded in a way stating that the Risk Register is used in the following plans would be more accurate. Any thoughts?
Thanks again..
mickcalcara
Thu, 07/01/2010 - 18:07
Permalink
I think I understand.
I failed to read the last sentence of page 350. “The following is a representative list of project management plan components and project documents.” So I guess saying one these is a component of the project management plan is accurate but not part of the project management plan. I still find this confusing.. I will be very careful on the Test when answering these type of questions Thanks