Question from Scordo

 Shawn is in the execution phase of his project. He is getting unexpected requests from his stakeholders about the project progress. All of the following can be used by Shawn to respond to their requests EXCEPT:

  1. The project management plan

  2. The stakeholder register

  3. Organizational process assets

  4. Performance reports

 

C

 

Regards.

 