The date through which the project has provided actual status and accomplishments is called:
-
Data Date (DD)
-
Due Date (DD)
-
Project Date (PD)
-
Reporting Date (RD)
Forums:


bkthakkar
Wed, 07/10/2013 - 11:26
Permalink
The Answer is A (Data
The Answer is A (Data Date),
See Page NO: 432, PMBOK (4th Edition)