Question
Submitted by Judy on Thu, 07/18/2013 - 21:06
I'm sure that I've just been looking at this stuff too long but I cannot understand how the answer was achieved?
Javier is completing his final project report. He includes information on the final variances. If the project was scheduled to take 12 months and it finishes in 14 months, what would Javier's final SPI results be?
a) 1
b) 1.17
c) 0.86
d) Not enough information to determine.
The answer is 1, but it's not clear to me why. Can anyone explain?
I was using SPI=EV/PV. SPI= 14/12
Forums:


svsatheeshkumar
Fri, 07/19/2013 - 00:14
Permalink
SPI after project finished
Since the project is finished, SPI will be 1 .
vikula01
Fri, 07/19/2013 - 00:53
Permalink
calculate
SPI = EV/PV
If the planned value of project is $X then when the project is finished the project will earn the $X - that means once project is completed earned value is equal to planned value - so SPI = 1
Judy
Fri, 07/19/2013 - 03:25
Permalink
Thank you.
Thank you.