Communication Channel
Submitted by Jewahir on Sun, 07/21/2013 - 18:16
please assist. When should I add the project manager and when not?
In some exams it adds +1 for the project manager. In the PMP exam, what is the right method to follow?
Forums:


ppalkonda1975
Sun, 07/21/2013 - 18:29
Permalink
according to me the question
according to me the question clearly tells the count and I had questions on this topic and it was clear...so i think no worries but in general rule PM is also a stakeholder and a communication channel
ramzy
Sun, 07/21/2013 - 21:49
Permalink
I would agree with the above
I would agree with the above comments as well.
Since the formula is straightforward, i would first read the question and if it does not explicitly mention or ask what is the communication channel including PM, i would calculate without first and look at the answer options.
Either way, the question would mention what it's looking for. Hope this helps!