Questions about CPI&SPI

 Question: If CPI=1 and SPI=0,8. What can you say about this project?


1)      Project on track.                       2)      Project is under budget and behind schedule.


 

admin's picture

 on budget and behind schedule

ditoo

Let us know if there are two options or more options exits.

 The answer is no. 2) The Project is under budget and behind schedule.

Please refer to PMBOK5 page 219

 The answer is no. 2) The Project is under budget and behind schedule.

Please refer to PMBOK5 page 219

What are the other options available?


When you have 1 as value, it indicates that your planed and actual is same. Less than 1 indicates you planned less than actual.


Here CPI is 1. So I was wondering whether we can call it under budget.


 

I agree the answer is the project is exactly at the planned budget and behind planned schedule.