Risk impact and probability

 Hi,

i see exams that associate risk probability and impact analysis in the Qualitative Analysis and some in the Quantitative Analysis. Reading the PMBOK it seems clear it is part the the Qualitative Analysis.

Is this correct? Any thoughts that would help clarify this?

thanks

admin's picture

 yes probablity and impact are for Qualitative. Risk is qualified by its probablity and impact, 

 probabibility and impact analysis is done in Qualitative analysis which is subjective. However the probabilistic analysis listing the possible completion or acheiveing time and cost objectives is done in Quatitative analysis..if the question states probablisitic analysis then this is done part of quatitative analysis which is the output of this process..

 Thanks for your help. So many details to remember!