Five tasks are scheduled to be completed in sequence. Each task has a finish-start relationship with the next task. Each has one day of total float. As of today, task one and two have been completed on schedule. How many days of float remain in the schedule of these tasks?
A. 1
B. 2
C. 4
D. 0
Forums:


admin
Fri, 01/03/2014 - 03:36
Permalink
Total Float - Amount of time
Total Float - Amount of time that an activity may be delayed from early start without delaying the project finish date.
Free Float - Amount of time a task can be delayed without delaying the early start of its successor.
So answer is 1