Oliver lehmann question

 Hello All

                    Another question, could someone please help me with this one? The answer is d.

 

During project planning, you are presented with the following diagram that depicts a cumulative likelihood distribution for the duration of a project: What kind of conclusion can you draw from the information depicted in it? 73

o The likeliness that the project will finish exactly at the date marked with "Deadline" is 80%.

o The likeliness that the project team will exceed the date marked with "Deadline" is at 80%.

o If the project team will meet the deadline, project costs will be 80% of the budgeted costs.

o The likeliness that the project team will meet the deadline or will finish earlier is at 80%.

 

AttachmentSize
Image icon quest.png22.22 KB

The correct answer is D.  Since the image shows the project team meets the deadline since the blueline comes to the duration of the X axes or its 80% complete when the graph meets the deadline.