Help pls!
Submitted by Latunde on Sun, 04/06/2014 - 00:54
Your project exceeded costs in the past caused by an underestimation of resource costs in the cost baseline:
PV: $1,200,000, EV: $1,000,000, AC: $1,200,000
You expect the underestimation to influence the future as much as it did in the past.
If the value of the remaining work (BAC – EV) is at $1,000,000, what should be your new EAC (estimate at completion)?
$1,800,000 o $2,000,000 o $2,200,000 o $2,400,000
The correct answer is 4 which is 2,400,000. How did they arrive at this and which formulas was used. Cause I used AC+ (Bac-Ev) which happen to be option 2
Forums:


vishwadeep
Sun, 04/06/2014 - 01:21
Permalink
Hi Again
"You expect the underestimation to influence the future as much as it did in the past."
Formulato be used is: BAC/CPI(cumulative)=EAC
vishwadeep
Sun, 04/06/2014 - 01:27
Permalink
Detail Calculation
vishwadeep
Sun, 04/06/2014 - 01:32
Permalink
Small corrections for clarity
Latunde
Sun, 04/06/2014 - 02:11
Permalink
Thanks. Much appreciated.
Thanks. Much appreciated.