Planning Package vs. Work Package
Submitted by philstinnet on Mon, 05/05/2014 - 16:36
Could anyone please clear my doubt?
Are Planning Package and Work Package the same thing ?
It can be seen on Page 132 - first paragraph of PMBOK.
Thanks
Forums:


admin
Tue, 05/06/2014 - 05:40
Permalink
Check this posthttp://pmzilla
Check this post
http://pmzilla.com/pmp-exam-tip-know-difference-between-planning-package-and-work-package
anmol2701
Tue, 05/06/2014 - 06:18
Permalink
Planning Package vs. Working package
Planning packages are created to describe work within a control account that will occur in the future
While
Work package is the work that has been planned and budgeted in detail.