A manager asks you to evaluate
A manager asks you to evaluate four new projects that he has suggested for next year. You review the projects and notice that one is not really a project, but more an operational task. Which of these is not a project?
1. Change the product to enable increased consumer usage
2. Manage a set of people for the next year to deliver the desired productivity results
3. Respond to a customer request for different product packaging
4. Resolve a space constraint issue by building a new addition to the plant
For the answer that you are choosing pls let us know WHY it does NOT have a definite start , end and/or produces an unique result.


ashwin
Mon, 06/02/2014 - 08:50
Permalink
2. Manage a set of people for
2. Manage a set of people for the next year to deliver the desired productivity results
Because this seems like and ongoing activity where the same work is being performed by a set of resources.
Meiyazhagan
Mon, 06/02/2014 - 09:03
Permalink
Manage a set of people for the next year to deliver the desired
As Manage a set of people for the next year to deliver the desired productivity results is repetitive work to manage humanresource, it wont come under project.
admin
Mon, 06/02/2014 - 09:34
Permalink
It says a TASK. Option 3 is a
It says a TASK. Option 3 is a task. Option 2 is a project since you have definite timelines and goals to achieve.
Jp2786
Mon, 06/02/2014 - 17:10
Permalink
For option B,
For option B, we have a definite start and end (Jan 2015 to dec 2015) and unique result : increased productivity
Then how can B be the answer?
Jp2786
Mon, 06/02/2014 - 17:10
Permalink
For option B,
For option B, we have a definite start and end (Jan 2015 to dec 2015) and unique result : increased productivity
Then how can B be the answer?
sunku65
Tue, 06/03/2014 - 15:29
Permalink
The option is 3.
The option is 3.
The customer asked different packaging products.
The Packaging products process comes into Manufacturing.
After mfg. products can be packaged in different type.
For example Sugar can packed like 200g,500g,1kg, 2kg , 5kg, 10kg or 20kg.
This is a process not a project.
Jp2786
Tue, 06/03/2014 - 17:34
Permalink
according to PMBOK
I think they have given option B as the answer because, according to PMBOK below are the reasons for which a project can be started
Market demand
Customer req
Business / social / legal
Environment need
Tech advancement
I guess B does not fall in of these categories. BTW this is from Kim Heldman and he says answer is B
Frances Tessler
Sat, 08/02/2014 - 15:02
Permalink
Project Definition
Characteristics of a project = PUT > Progressively Elaborated, Unique, and Temporary.
Managing a group of people to deliver productivity results is ongoing activities and is not a project.